Orders: how long will it take?
# FAQ 2 min read
Our standard lead-time is based on the estimated supply and fabrication time for our made-to-order products. We operate on a lead-time minimum of 25 business days based on typical supply chain logistics.
Once you have signed-off on your quote and paid the required deposit, at this point we consider the order confirmed. Our standard lead-time is based on the estimated supply and fabrication time for our made-to-order products.
- The aluminium extrusions required to make the frames and panels for the products are extruded in Brisbane and powder-coated as a batch for your order and takes between 15-20 days to arrive from the supplier
- There are thousands of extrusion profiles across the product series therefore we only order what is required to manufacture the products in your order.
- We do not keep stock of products in standard-sizes, each item is made specifically for your project.
To achieve the standard advised lead-time, a site measure meeting should occur within 7 days of placing your order.
- Special-order products such as Centor Retractable and FlowTHRU drain systems have a separate lead-time from their manufacturer. These items need to be confirmed and ordered as soon as possible as the supplier lead-times can vary depending on supply chains.
- Glass is ordered only after the site-measure meeting has taken place to confirm the manufacture sizes, this can take up to 10 days to arrive to our factory.
- Assembly process begins once all the Extrusion, Components and Glass materials have arrived